POWER INDUSTRY, FUEL
INDUSTRY
INVESTMENT PROJECT ¹ 1
Name of the project: Modernization of hydroelectric
power station - 1, hydroelectric power station - 2 of the
stage of varzob hydroelectric power station
Title of enterprise: OPEN HOLDING JOINT STOCK COMPANY
" BARKI TOJIK "
Address: 734026, Republic of Tajikistan, Dushanbe,
64 Ismoili Somoni street.
Telegraph: Dushanbe " Barki Tojik ", teletype:
201261 "Plamya"
Tel.: (992-372) 35-86-68, fax: (992-372) 35-86-92
E-mail: e-mail-barki tojik@tajnet.com
Field of activity: manufacture, transmission and distribution
of thermal and electrical energy
The purpose of the project: improvement of manufacture, transmission
and distribution of the electric power by an rehabilitation
and modernization of the existing equipment.
The brief description of the project: For the modernization
of the Varzob Stage the Hydroelectric Power Station - 1 it
is necessary to exchange the turbine with the turbine type
of HYDROELECTRIC POWER STATION - 1 PO 75/702. To establish
the transformer TM-4000 êVÀ , 35/6 kV, to elaborate distance
control of shields GU HYDROELECTRIC POWER STATION - 2.
On HYDROELECTRIC POWER STATION - 2: to exchange existing turbines
such as PO 115/697, to construct automatic free - running
drop. To exchange the existing transformer, to adjust steady
and reliable operation of generators. To establish reactors
concrete - copper on diverging lines of generating, second
generator 25000 êVÀ on 110/35/10 kV, disk shutters.
Overall costs of the project:
(Million. US dollars) - 9,0
From them:
Own means:
The external investments - 9,0
The proposal to investors:
Possible forms of co-operation:
Engaging of the investments by the way of credit
Document ground of the project:
The technical - economical substantiation.
Business - plan.
--------------------------------------------------------------------------------------------------------
INVESTMENT PROJECT ¹ 2
Name of the project: Building of substation 220 êv
"shahrinav"
Title of firm: OPEN HOLDING JOINT - STOCK COMPANY "
BARKI TOJIK "
Address: 734026, Republic of Tajikistan,. Dushanbe,
64 Ismoili Somoni street
Telegraph: Dushanbe " Barki Tojik " the teletype:
201261 "Plamya"
Tel.: (992-372) 35-86-68, fax: (992-372) 35-86-92
E-mail: e-mail-barki tojik@tajnet.com
Field of activity: manufacture, transmission and distribution
of thermal and electrical energy
The purpose of the project: improvement of electrical power
supply of Gissar Region.
The brief description of the project: For liquidation of a
deficit in power junctions of Dushanbe, Shahrinav and Gissar
regions it is necessary to build the new supporting PC 220
êV with two autotransformers on 125 thousand êVÀ each and
one autotransformer
125 êVÀ
Overall costs of the project:
(million. US dollars) - 8,854
from them:
own means
the external investments -8,854
The proposal to the investors
Possible forms of co-operation:
Engaging of the investments by the way of credit
Document ground of the project:
The technical - economical substantiation.
Business - plan.
-----------------------------------------------------------------------------------------------------------
INVESTMENT PROJECT ¹ 3
Name of the project: Modernization of kayrakum hydroelectric
power station
Title of the enterprise: OPEN HOLDING JOINT - STOCK
COMPANY " BARKI TOJIK "
Address: 734026, Republic of Tajikistan,. Dushanbe,
64 Ismoili Somoni street
Telegraph: Dushanbe " Barki Tojik " the teletype:
201261 "Plamya"
Tel.: (992-372) 35-86-68, fax: (992-372) 35-86-92
E-mail: e-mail-barki tojik@tajnet.com
Field of activity: manufacture, transmission and distribution
of thermal and electrical energy
The purpose of the project: increase of reliability of effecting,
transmission and distribution of the electric power by modernization
of the existing equipment of a hydropower plant.
The brief description of the project: To execute an estimation
of residual resource of the hydraulic turbines which have
fulfilled the normative service life. The replacement of power
equipment, taking in to account the design features of the
hydrounit, replacement of the runner, modernization of hydrogenerators
with usage of new technology ÎÐÓ, drainage pompes and compressors,
replacement of oil and air circuit breakers is indispensable.
Overall costs of the project:
(million. US dollars) - 26,8
from them:
own means
the external investments -26,8
Proposal to investors
Possible forms of co-operation:
Engaging of the investments by the way of credit
Document ground of the project:
The technical - economical substantiation.
Business - plan.
---------------------------------------------------------------------------------------------------------------
INVESTMENT PROJECT ¹ 4
Name of the project: Modernization of the fall casting
hydroelectric power station
Title of enterprise: OPEN HOLDING JOINT - STOCK COMPANY
" BARKI TOJIK "
Address: 734026, Republic of Tajikistan,. Dushanbe,
64 Ismoili Somoni street
Telegraph: Dushanbe " Barki Tojik " the Teletype:
201261 "Plamya"
Tel.: (992-372) 35-86-68, fax: (992-372) 35-86-92
E-mail: e-mail-barkitojik@tajnet.com
Field of activity: Manufacture, transmission and distribution
of thermal and electrical energy
The purpose of the project: improvement of manufacture of
the electric power by the modernization of the existing equipment.
The brief description of the project: modernization of hydraulic
units No: 1, No: 2, No: 3. Replacement of accumulator batteries,
compressors, rehabilitation of a piezometrian network on hydraulic
engineering facilities, realization of shore strengthening
activities on derivational channel.
Overall costs of the project:
(million. US dollars) - 16,2
from them:
own means
the external investments -16,2
Proposal to the investors
Possible forms of co-operation:
Engaging of the investments by the way of credit
Document ground of the project:
The technical - economical substantiation.
Business - plan.
----------------------------------------------------------------------------------------------------------
INVESTMENT PROJECT ¹ 5
Name of the project: Reconstruction of distributive
electrical networks.
Title of enterprise: OPEN HOLDING JOINT - STOCK COMPANY
" BARKI TOJIK "
Address: 734026, Republic of Tajikistan,. Dushanbe,
64 Ismoili Somoni street
Telegraph: Dushanbe " Barki Tojik " the Teletype:
201261 "Plamya"
Tel: (992-372) 35-86-68, fax: (992-372) 35-86-92
E-mail: e-mail-barki tojik@tajnet.com
Field of activity: manufacture, transmission and distribution
of thermal and electrical energy
The purpose of the project: an improvement of the quality,
reliability of transmission and distribution of the electric
power.
The brief description of the project: the replacement of existing
transformers on more powerful is indispensable in order to
decrease the load of existing distributive electrical circuits
networks. A rewiring (on the greater cross-section), bearings,
disconnecting switches, disconnectors, single-switches, automatic
control units, safety devices. Building of additional substations
6-10-20 / 0,4 sq.
Overall costs of the project:
(million. US dollars) - 70,0
from them:
own means
the external investments -70,0
The proposal to the investors
Possible forms of co-operation:
Engaging of the investments by the way of credit
Document ground of the project:
The technical - economical substantiation.
Business - plan.
---------------------------------------------------------------------------------------------------------
INVESTMENT PROJECT ¹ 6
Name of the project: Reconstruction of a park of the
count in a power system Open Holding Joint - Stock Company
" Barki Tojik "
Title of firm: OPEN HOLDING JOINT - STOCK COMPANY "
BARKI TOJIK "
Address: 734026, Republic of Tajikistan,. Dushanbe,
64 Ismoili Somoni street
Telegraph: Dushanbe " Barki Tojik " the Teletype:
201261 "Plamya"
Tel: (992-372) 35-86-68, fax: (992-372) 35-86-92
E-mail: e-mail-barki tojik@tajnet.com
Field of activity: manufacture, transmission and distribution
of thermal and electrical energy
The purpose of the project: achievement of the qualitative
calculation of the consumed electric power in a power system
Open Holding Joint - Stock Company " Barki Tojik "
The brief description of the project: used devices for calculation
of the electric power morally and physically have become outdated,
as have a poor nonsufficient accuracy, create disculculation
of consumed electric power, do not have the possibility of
operating control of routine-limit discipline.
It is indispensable the full replacement of an existing park
of devices of the calculation on modern electronic meters
with absolute consistency for:
1. Intergovernmental crossflow of the electric power in quantity
66 pieces with an absolute consistency 0,2.
2. Development of diverging lines in quantity 135 pieces with
an absolute consistency 0,5
3. Head count in quantity 300 pieces with an absolute consistency
0,5.
4. Interregional counting in quantity 280 pieces with an absolute
consistency 1,0
5. Technical count in quantity 4500 pieces with an absolute
consistency 1,0
Total 5281 pcs. of electric meters.
The application of electric meters demands partial replacement
of measuring transformers of a current and voltage.
Simultaneously with it the conforming metrology equipment,
computer means and communication facilities, and also replacement
of electric meters for the household users which are most
power-intensive are required.
Overall costs of the project:
(million. US dollars) - 15,04
from them:
own means
the external investments -15,04
The proposal to the investors
Possible forms of co-operation:
Engaging of the investments by the way of credit
Document ground of the project:
The technical - economical substantiation.
Business - plan.
=============================================================
INVESTMENT PROJECT ¹ 7
Name of the project: Recovery of producing of transformers.
Title of enterprise: OPEN JOINT STOCK COMPANY "TRANSFORMATOR".
Address: 735140, Republic of Tajikistan, Khatlon Region,.
Kurgan - Teppa, 1 Gafurova Street
Tel: (109923222) 2-37-53, 2-43-15, 2-21-64, fax: (992372)
21-82-81 ( Dushanbe)
Field of activity: The manufacture of power transformers
and measurement aparatus.
The purpose of the project: The recovery of the manufacture
and expansion of output, full loading of existing powers for
fulfillment of demand inside the republic, and also export
to other countries.
The brief description of the project: Realization of maintenance-rehabilitation
activities, replacement of the obsolete equipment, realization
of starting-up and adjustment works, acquisition of spares
parts, furnishing components, raw and materials which are
indispensable for operation of the manufacture.
Overall costs of the project:
(million. US dollars) - 3,1
from them:
own means - 0,6
the external investments -2,5
payback time (year) - 3
The proposal to the investors
Possible forms of co-operation:
Creation of joint venture including of foreign investors
Documentary ground of the project:
Investment project.
Business - plan.
-------------------------------------------------------------------------------------
INVESTMENT PROJECT ¹ 8
Name of the project: Building of oil-refining factory
in Hissar urban settlement of the Republic of Tajikistan.
Enterprise name: Limited Enterprise "KNOW - HOW"
Address: 77, Mushfiki str., Dushanbe city, RT, 734025
Òål.: (992-372) 27-35-28.
E-mail: saijafav@mail.ru
Activity type: Oil products treatment.
Project goal: Building of oil-refining factory.
Brief description of the project: Erection woks, purchasing
of equipment. Annual productivity of the factory will make:
- petrole - 7000 t;
- diesel fuel - 20000 t;
- black oil (furnace) - 27000 t.
Total project cost:
(million US dollars) - 1,320
of which:
own contributions -
foreign investments - 1,320
recoupment time (year) - 0,21
Proposal to investors
Possible forms of cooperation:
Attracting investments in the form of a credit:
Documental justification of the project:
Investment project
Business - plan.
|